To generate $20,000 per month primarily from electricity sales to the ERCOT grid, here’s what you’d need. “This offering is made pursuant to Rule 506(c) of Regulation D under the Securities Act of 1933.” jamespolk.net/private-offering It also backs Christian Victim Advocacy for Sex-Trafficking Victims via praxisprofessional.com:
⚡ Minimal Viable Generation Buildout Plan
✅ Target Income
-
Monthly Net Profit: $20,000
-
Revenue Source: Grid electricity sales (ERCOT West Zone)
Technical Specs
-
Required Capacity: ~0.40 MW (~400 kW)
-
Estimated Buildout Cost: ~$714,000
-
Based on $1.8M per MW gas-fired generator cost
-
Includes gas engine, sitework, interconnection prep, and grid-ready equipment
-
️ Strategy
-
Initial Focus: Pure electricity generation to ERCOT grid
-
BTC Mining Expansion Plan:
-
Allocate pad space and power panel for future containers
-
Add 50–100 kW of miners over time, behind the meter
-
BTC profits reinvested into scaling mining gear up to ~0.4 MW
-
Licensing Needs (Same as Full Project)
-
TCEQ Air Permit (minor source)
-
TDSP Generator Interconnection Request (local utility like Oncor)
-
Ector County building/electrical permits
-
Business registration under Apex Centinel Trust